FG Orders Suspension Of Eleme-Onne East-West Road Construction

-

- Advertisment -

The Tinubu-led Federal Government has suspended the reconstruction work along the Eleme-Onne portion of the East-West Road in Rivers State.

In an interview with reporters on Sunday in Port Harcourt, the Minister of Works, David Umahi, disclosed that the suspension directive was issued following the discovery that the contractor managing the project used inferior materials.

He expressed disappointment over the poor progress of construction despite the government having paid an advance of N33 billion, even though he mentioned that he had viewed the work the day before (Saturday).

The Minister clarified that the work must cease until some anomalies related to the project are fixed, stating that the contractors’ current rate of work will not allow the job to be finished in five years.

The minister said, “The project must benefit the people. The rainy season is coming in two months and the people will go ahead suffering.

“You have our (FB) N33 billion. Do you know what the interest rate is every month on the bill?

“The President had to order me in September to come here and order the payment because some people in Rivers State went to see the President and we paid you N33 billion, since that time till now.

“I saw that the sand they are using is not river sharp. What we paid for is river sharp sand.

“I’m not satisfied. The idea is that when you place the lumps, the lump would be good. But when you place the sharp sand there are some voids between the lumps.

“And so the sand will go and fill it and it becomes a compact monolithic pavement structure. When I saw that sand I wasn’t happy.

“And I took that sand and put it on my palm and poured water and I was squizzing it, and at the end of the day, there was nothing left.

“That confirmed that it was very clear. So I directed that the company should be written and they should ensure that they remove the sand.

“I was very shocked that instead of removing the sand they had continued with the sand.

“The contractor is carrying out the job, but at snail speed. If we allow him even another five years he will not finish So we are not going to allow him.”

To guarantee the project is finished, he added, a meeting with the contractor has been set up to examine the irregularities. Following that, the mistakes will be examined and a revised schedule will be provided.

Latest news

I bought female robot because Nigerian girls are stressing me – Content Creator, Brain Jotter

Nigerian comedian and content creator, Chukwuebuka...

Google’s Pixel Watch 5 Can Now Detect Breathing Emergencies

Google's first smartwatch debuted just four years ago, and at the time, the company went to great lengths to...

4 New Camera Tricks on Google’s Latest Pixel 11 Smartphones

Google's Pixel Camera chief, Isaac Reynolds, thinks year-to-year upgrades to smartphone cameras are still critical, even though some detractors...

Google Pixel 11 Series, Pixel Watch 5, Pixel Tag: Specs, Features, Price, Release Date

Google is dialing things up to 11 this year with its Pixel phones. Ahead of its annual Made by...
- Advertisement -

Honor’s Robot Phone Has a Gimbal-Powered Camera for Vloggers

You hear it often: Smartphones have plateaued. A small boost to battery life here, a minor camera upgrade there—our...

This Coin-Sized Device Can Hack a Boeing 737

Even as the digital components of so many life-critical systems have proven susceptible to cybersabotage—cars, medical devices, even water...

Must read

- Advertisement -

You might also likeRELATED
Recommended to you